Construction of new Boundary wall around Plant estimate

Sr.no Description Qty Rate Unit Amount
1 Earth work in excavation by mechanical
means (Hydraulic excavator) / manual
means in foundation trenches or drains
(not exceeding 1.5 m in width or 10 sqm
on plan) including dressing of sides and
 ramming of bottoms, lift up to 1.5 m,
 including getting out the excavated
soil and disposal of surplus excavated
soil as directed, within a lead of 50 m.
All kinds of soil.
17.64 181.85 M3 3207.83
2 Filling in plinth with sand under floors
including watering, ramming,
consolidating and dressing complete
 up to 10 ton
1.47 398.00 M3 585.06
3 Providing and laying in position cement
 concrete of specified grade excluding
the cost of centering and shuttering -
All work up to plinth level: 1:4:8
 (1 cement: 4 fine sands 8 graded
stone aggregate 40 mm nominal size)
1.47 5789.60 M3 8510.71
4 Providing and laying in position specified
 grade of reinforced cement concrete
excluding the cost of centering,
shuttering, finishing and reinforcement
- All work up to plinth level: 1:1.5:3
 (1 cement: 1.5 coarse sand: 3 graded
 stone aggregate 20 mm nominal size)
4.13 7718.25 M3 31840.68
5 Reinforced cement concrete work in
wall (any thickness), including attached
pilasters, buttresses, plinth and string
courses, fillets, columns, pillars, piers,
abutments, posts and struts etc. above
plinth level up to floor five level,
excluding cost of centering shuttering,
 finishing and reinforcement: 1:1.5:3
 (1 cement :1.5 coarse sand (zone iii) :
3 graded stone aggregate 20 mm
nominal size
4.04 9306.00 CUM 37619.51
6 Reinforced cement concrete work in
beams, suspended floor, roofs, having
slope up to 15 landing, balconies,
 shelves, chajjas, lintels, bands, plain
windowsills, staircase and spiral
staircases above plinth level up to
 floor five level, excluding the cost
of centering, shuttering, finishing
and reinforcement with 1:1.5:3
(1 cement: 1.5 coarse sand
(zone III): 3 graded stone aggregate
 20 mm nominal size
3.02 9763.80 CUM 29457.63
7 Steel reinforcement for R.C.C. work
including straightening, cutting,
bending, placing in position and
binding all complete up to plinth
level: Thermo-Mechanically
Treated bars of grade Fe-500D
or more.
1200.00 83.50 kg 100200.00
8 Brick work using common burnt clay
building brick having crushing
strength not less than 35 kg/sq.cm.
in foundation and plinth in cement
mortar 1:6 (1 cement :6 fine sand)
0.00 2548.71 CUM 0.00
9 Brick work using common burnt
clay building brick having crushing
strength not less than 35 kg/sq.cm.
in foundation and plinth in cement
mortar 1:6 (1 cement :6 fine sand)
(B) Conventional extra Brick work
in super structure above plinth level
up to two level (B)Conventional
6.13+6.19 (2936.64+160.96)=3097.6
17.58 2709.67 CUM 47647.04
10 15mm cement plaster on the rough
 side of single or half brick wall of
mix 1:6 ( 1 cement: 6 fine sand).
186.90 292.85 M2 54733.67
11 Finishing wall with water proofing
cement paint of required shade :
13.44.1 New work (Two or more
coats applied @ 3.84 kg/10sq.m)
186.90 91.25 M2 17054.63
12 Providing and fixing concertina
coil fencing with punched tap
concertina coil 600 mm Dia 10
meter openable length (total length
90 m ) having 50 no's rounds per 6
meter length, up to 3 m height of
wall with existing angle iron 'Y'
shape placed 2.4 m or 3.0 m apart
and with 9 horizontals R.B.T.
reinforced barbed wire, stud tied
with G.I. staples and G.I clips to
retain horizontal including necessary
bolts or G.I barbed wire tied to angle
iron all complete as per direction of
Engineer-in-charge with reinforced
barbed tape (R.B.T)/spring core
(2.5 mm thick) wire of high tensile
strength of 165 kg/sq.mm with tape
(0.52 mm thick) and weight 43.478
gm/meter (cost of M.S angle, C.C.
blocks shall be paid separately)
30.00 290.80 RMT 8724.00
13 structural steel work riveted bolted
or welded in built up sections,
trusses, fixing and position and
applying a priming coat of approved
 steel primer all complete
72.00 101.75 KG 7326.00
14 Painting with synthetic enamel paint
of approved brand and manufacture
to give an even shade : 13.61.1 Two
or more coats on new work
3.20 121.55 M2 388.96
15 Centering and shuttering including
strutting, propping etc. and removal
of form for all heights :
Foundations, footings, bases of
columns, etc. for mass concrete
24.19 284.85 M2 6890.52
Column, Piller, Piers, Abutment,
post and struts
44.10 773.70 M2 34120.17
Lintel, beams, plinth beams, girders,
bressummers and cantilevers.
27.83 552.05 M2 15360.79
TOTAL 403667.19
Estimated cost of 30 m. 403667.19
Measurment sheet
considerering 30.00 M length
No of column @ 3.00 m C/C =30 /3.00+1 =11 nos of column
Item no Items No Length Breadth Depth Quantity unit
1 Earthwork in foundation excavation
up to 1.5m depth.
for Column footing 9 1.20 1.20 1.20 15.55
for extra column pad 1 1.45 1.20 1.20 2.09
17.64 M3
2 Filling in plinth with sand under floor
in footing 9 1.20 1.20 0.10 1.30
for extra column pad 1 1.45 1.20 0.10 0.17
1.47 M3
3 Providing and laying in position
cement concrete of specified: 1:4:8
(1 cement: 4 fine sands 8 graded
stone aggregate 40 mm nominal size)
for footing 9 1.20 1.20 0.10 1.30
for extra column pad 1 1.45 1.20 0.10 0.17
1.47 M3
4 Providing and laying in position
specified grade of reinforced
cement concrete 1:1.5:3 (below plinth)
footing 9 1.00 1.00 0.25 2.25
column 9 0.35 0.35 0.95 1.05
Length = 1.2-0.25 = 0.95 m
for extra column pad footing 1 1.45 1.00 0.25 0.36
for extra column pad 2 0.70 0.35 0.95 0.47
4.13 M3
5 reinforced cement concrete
1:1.5:3 in column (above plinth)
above plinth level column 9 0.35 0.35 3.00 3.31
for double footing 1 0.70 0.35 3.00 0.74
4.04 M3
6 reinforced cement concrete
1:1.5:3 in beam
for plinth beam 10 2.65 0.23 0.38 2.29
11 column 10 span
for coping 10 2.65 0.23 0.12 0.73
3.02 M3
7 Steel reinforcement for R.C.C.
work, up to plinth +column
beams @ 100kg/cum
5.48+4.04+3.02=12.54 cum 1 12 100 1200.00 kg
8 Brick work in foundation &
plinth in cement mortar 1:6
0.00
Total 0.00 cum
9 Brick work in super structure
 in cement mortar 1:6
10 2.65 0.23 2.89 17.58
Total 17.58 cum
10 15mm cement plaster on the
rough side of single or half
brick wall of mix 1:6 (1
cement: 6 fine sand).
for wall 1x2 30.00 3.00 180.00
wall top 1x1 30.00 0.23 6.90
Total 186.90 M2
11 Finishing wall with water
 proofing cement paint of
required shade :13.44.1 New
 work (Two or more coats
applied @ 3.84 kg/10sq.m)
same as item no-10 186.90 M2
12 Providing and fixing concertina
coil fencing with punched tap
concertina coil 600 mm Dia 10
meter openable length (total
length 90 m ) having 50 no's
rounds per 6-meter length, up
to 3 m height of wall with
existing angle iron 'Y' shape
placed 2.4 m or 3.0 m apart
and with 9 horizontals R.B.T.
reinforced barbed wire, stud
tied with G.I. staples and G.I
clips to retain horizontal
including necessary bolts or
G.I barbed wire tied to angle
iron all complete as per
direction of Engineer-in-charge
 with reinforced barbed tape
(R.B.T)/spring core (2.5 mm
 thick) wire of high tensile
strength of 165 kg/sq.mm with
tape (0.52 mm thick) and weight
 43.478 gm/metre (cost of M.S
angle, C.C. blocks shall be paid
separately)
1 1 30 30.00 Rmt
13 structural steel work riveted
bolted or welded in built up
sections, trusses, fixing and
position and applying a
priming coat of approved
steel primer all complete
10 1.6 16.00 Rmt
wt @ 4.50 kg/m 4.50
72.00 kg
14 Painting with synthetic enamel
paint of approved brand and
manufacture to give an even shade
: 13.61.1 Two or more coats
on new work
10 1.6 0.20 3.20 M2
15 Centering and shuttering
including strutting, propping
etc. and removal of form for
all heights :
A Foundations, footings,
bases of columns, etc.
for mass concrete
Foundation 9x4 1.00 0.25 9.00
Column 9x4 0.35 0.95 11.97
for extra column pad 1x2 1.45 0.25 0.73
1x2 1.00 0.25 0.50
column 1x2 0.70 0.95 1.33
1x2 0.35 0.95 0.67
24.19 M2
B Column, Piller, Piers,
Abutment, post and struts
column 9x4 0.35 3.00 37.80
for extra column pad 1x2 0.70 3 4.20
1x2 0.35 3.00 2.10
44.10 M2
C Lintel, beams, plinth beams, girders, bressummers and
cantilevers.
Beam 10x2 2.65 0.38 19.88
coping 10x2 2.65 0.15 7.95
27.83 M2
Construction of new Boundary wall around Plant estimate Construction of new Boundary wall around Plant estimate Reviewed by civil engineer on August 13, 2024 Rating: 5