🏗️ RCC Concrete Quantity Calculation: Footing (C1-C13), Column up to Plinth & Ground Beam (GB1-GB25) as per IS 456
Isolated Trapezoidal Footing | Column Concrete up to Plinth Level | Ground Beam RCC | Complete BOQ with Schedules
📥 Download Complete RCC Concrete BOQ Excel Sheet
Join our WhatsApp channel to get the complete Excel measurement sheet with all footing (C1 to C13), column up to plinth, and ground beam (GB1 to GB25) concrete calculations.
📱 Join WhatsApp Channel 📥 Download Excel BOQ Sheet (RCC Concrete)📊 Excel file includes: Trapezoidal footing calculation for C1-C13 (346.26 cu.ft) | Column up to plinth (67.88 cu.ft) | Ground beam GB1-GB25 (197.53 cu.ft) | Abstract summary | Unit conversion (cu.ft to cu.m)
📐 RCC Schedules - Ground Beam Schedule & Footing/Column Schedule
📑 Jump to Section:
- IS 456:2000 - Code of practice for plain and reinforced concrete (M20/M25 grade specifications)
- IS 1200 (Part 2):1974 - Method of measurement of building and civil engineering works – Concrete works
- IS 10262:2019 - Concrete mix proportioning guidelines for RCC
- IS 1786:2008 - Specification for high strength deformed steel bars (reinforcement)
- CPWD Specifications (Vol. I & II) - Standard specifications for RCC work and execution
📐 Trapezoidal Footing Formula
Volume of Trapezoidal Portion = h/3 × (A₁ + A₂ + √(A₁ × A₂))
Where: A₁ = Bottom Area (L×B), A₂ = Top Area (L×B), h = Height of trapezoidal portion
📊 Isolated Footing Concrete Measurement Sheet (C1 to C13)
| Footing ID | No. | Bottom L×B (ft) | Top L×B (ft) | Trapezoidal Height (ft) | Quantity (cu.ft) | Quantity (cum) |
|---|---|---|---|---|---|---|
| Trapezoidal Footing Calculation for C1 to C13 as per drawing dimensions | ||||||
| C1, C10 | 2 | 4.75×4.5 | 1.25×1.75 | 1.0 | 52.11 | 1.48 |
| C2, C4, C5, C7, C8, C9 | 6 | 5.0×4.75 | 1.25×1.75 | 1.0 | 168.72 | 4.78 |
| C3, C11 | 2 | 4.75×4.5 | 1.25×1.75 | 1.0 | 50.50 | 1.43 |
| C6 | 1 | 5.25×4.75 | 1.25×1.75 | 1.0 | 31.81 | 0.90 |
| C12 | 1 | 4.5×4.25 | 1.25×1.75 | 1.0 | 22.62 | 0.64 |
| C13 | 1 | 4.25×4.0 | 1.25×1.75 | 1.0 | 20.50 | 0.58 |
| Total Footing Concrete Quantity (C1 to C13) | 346.26 cu.ft | 9.81 cum | ||||
📌 Sample Calculation for C1 Footing (Trapezoidal)
Bottom Portion: Length 4.75 ft × Width 4.5 ft × Depth 0.75 ft = 16.03 cu.ft
Trapezoidal Portion: h/3 × (A₁ + A₂ + √(A₁×A₂)) = 1/3 × (21.375 + 2.1875 + 6.84) = 10.02 cu.ft
Total for 1 footing (C1): 16.03 + 10.02 = 26.05 cu.ft (0.74 cum)
For C1 & C10 (2 footings): 26.05 × 2 = 52.11 cu.ft (1.48 cum)
📊 Column Concrete Measurement Sheet (Up to Plinth)
| Column ID | No. | Length (ft) | Width (ft) | Height (ft) | Quantity (cu.ft) | Quantity (cum) |
|---|---|---|---|---|---|---|
| Columns C1 to C13 up to plinth level - dimensions as per structural drawing | ||||||
| C1 to C13 | 13 | As per column schedule drawing | 67.88 | 1.92 | ||
| Total Column Concrete (C1 to C13 up to Plinth) | 67.88 cu.ft | 1.92 cum | ||||
📊 Ground Beam Concrete Measurement Sheet (GB1 to GB25)
| Beam ID | No. | Length (ft) | Breadth (ft) | Depth (ft) | Quantity (cu.ft) | Quantity (cum) |
|---|---|---|---|---|---|---|
| Ground Beams GB1 to GB25 (9"×15" and 6"×15") - as per structural drawing | ||||||
| GB1 to GB25 | 25 | As per ground beam schedule drawing | 197.53 | 5.60 | ||
| Total Ground Beam Concrete Quantity (GB1 to GB25) | 197.53 cu.ft | 5.60 cum | ||||
= 346.26 + 67.88 + 197.53 = 611.67 cu.ft
= 17.32 cum (1 cu.m = 35.315 cu.ft)
| S.No | Component | Quantity (cu.ft) | Quantity (cum) | IS Code Reference |
|---|---|---|---|---|
| 1 注意: 按照完整楼板计算 根据图纸尺寸:23 ft × 36.5 ft Note: Complete slab calculation - The area includes all spaces between beams. Full plinth area shall be cast. |
Isolated Trapezoidal Footing (C1 to C13) | 346.26 | 9.81 | IS 456:2000 |
| 2 | Column up to Plinth (C1 to C13) | 67.88 | 1.92 | IS 456:2000 |
| 3 | Ground Beam (GB1 to GB25) | 197.53 | 5.60 | IS 456:2000 |
| GRAND TOTAL | RCC Concrete Quantity | 611.67 cu.ft | 17.32 cum | As per IS 1200 (Part 2):1974 |
📌 Deduction Norms as per IS 1200 (Part 2):1974 Clause 2.1.2:
- NO DEDUCTION shall be made for volume occupied by reinforcement steel bars (up to 2% of concrete volume).
- NO DEDUCTION for formwork or small openings up to 0.1 sqm in cross-section.
- Conclusion: Full measured volume of 611.67 cu.ft (17.32 cum) is billable for RCC concrete work.
📋 Final RCC Concrete Billing Statement (Footing + Column + Ground Beam)
| Particulars | Quantity (m³) | Rate (₹) | Amount (₹) |
|---|---|---|---|
| RCC Concrete (M20/M25 grade) for Isolated Footing C1-C13 + Column up to Plinth C1-C13 + Ground Beam GB1-GB25 including formwork, mixing, laying, compaction, and curing | 17.32 | 5,500 | 95,260 |
| Total Basic Cost (Including Contractor Profit & Water Charges) | 95,260 | ||
| Add: GST @ 18% | 17,147 | ||
| GRAND TOTAL (RCC Concrete Only) | ₹ 1,12,407 |