RCC Concrete Quantity Calculation

Footing, Column & Ground Beam Concrete Quantity | RCC BOQ as per IS 456 | Civil Engineering

🏗️ RCC Concrete Quantity Calculation: Footing (C1-C13), Column up to Plinth & Ground Beam (GB1-GB25) as per IS 456

Isolated Trapezoidal Footing | Column Concrete up to Plinth Level | Ground Beam RCC | Complete BOQ with Schedules

✓ IS 456:2000 | IS 1200 (Part 2):1974 | CPWD DSR 2026 | M20/M25 Grade Concrete

📥 Download Complete RCC Concrete BOQ Excel Sheet

Join our WhatsApp channel to get the complete Excel measurement sheet with all footing (C1 to C13), column up to plinth, and ground beam (GB1 to GB25) concrete calculations.

📱 Join WhatsApp Channel 📥 Download Excel BOQ Sheet (RCC Concrete)
⚠️ Join WhatsApp channel first to unlock Excel download

📊 Excel file includes: Trapezoidal footing calculation for C1-C13 (346.26 cu.ft) | Column up to plinth (67.88 cu.ft) | Ground beam GB1-GB25 (197.53 cu.ft) | Abstract summary | Unit conversion (cu.ft to cu.m)

📐 RCC Schedules - Ground Beam Schedule & Footing/Column Schedule

Ground Beam Schedule - GB1 to GB25 with reinforcement details
📋 Figure 1: Ground Beam Schedule (GB1 to GB25) - Reinforcement details as per structural drawing
Footing and Column Schedule - C1 to C13 with dimensions
📋 Figure 2: Footing and Column Schedule (C1 to C13) - Dimensions and reinforcement details
📜 Relevant IS Codes for RCC Concrete Measurement
  • IS 456:2000 - Code of practice for plain and reinforced concrete (M20/M25 grade specifications)
  • IS 1200 (Part 2):1974 - Method of measurement of building and civil engineering works – Concrete works
  • IS 10262:2019 - Concrete mix proportioning guidelines for RCC
  • IS 1786:2008 - Specification for high strength deformed steel bars (reinforcement)
  • CPWD Specifications (Vol. I & II) - Standard specifications for RCC work and execution
📐 A. Isolated Trapezoidal Footing Concrete Quantity (C1 to C13)
Trapezoidal footing calculation using formula method as per IS 456:2000

📐 Trapezoidal Footing Formula

Total Volume = Volume of Bottom Rectangular Portion + Volume of Trapezoidal Portion

Volume of Trapezoidal Portion = h/3 × (A₁ + A₂ + √(A₁ × A₂))
Where: A₁ = Bottom Area (L×B), A₂ = Top Area (L×B), h = Height of trapezoidal portion

📊 Isolated Footing Concrete Measurement Sheet (C1 to C13)

Footing IDNo.Bottom L×B (ft)Top L×B (ft)Trapezoidal Height (ft)Quantity (cu.ft)Quantity (cum)
Trapezoidal Footing Calculation for C1 to C13 as per drawing dimensions
C1, C1024.75×4.51.25×1.751.052.111.48
C2, C4, C5, C7, C8, C965.0×4.751.25×1.751.0168.724.78
C3, C1124.75×4.51.25×1.751.050.501.43
C615.25×4.751.25×1.751.031.810.90
C1214.5×4.251.25×1.751.022.620.64
C1314.25×4.01.25×1.751.020.500.58
Total Footing Concrete Quantity (C1 to C13)346.26 cu.ft9.81 cum

📌 Sample Calculation for C1 Footing (Trapezoidal)

Bottom Portion: Length 4.75 ft × Width 4.5 ft × Depth 0.75 ft = 16.03 cu.ft

Trapezoidal Portion: h/3 × (A₁ + A₂ + √(A₁×A₂)) = 1/3 × (21.375 + 2.1875 + 6.84) = 10.02 cu.ft

Total for 1 footing (C1): 16.03 + 10.02 = 26.05 cu.ft (0.74 cum)

For C1 & C10 (2 footings): 26.05 × 2 = 52.11 cu.ft (1.48 cum)

📊 B. Column Concrete Quantity (Up to Plinth Level - C1 to C13)
RCC column from footing top to plinth level as per IS 456
📐 Formula: Column Concrete Quantity = Number × Length × Width × Height

📊 Column Concrete Measurement Sheet (Up to Plinth)

Column IDNo.Length (ft)Width (ft)Height (ft)Quantity (cu.ft)Quantity (cum)
Columns C1 to C13 up to plinth level - dimensions as per structural drawing
C1 to C1313As per column schedule drawing67.881.92
Total Column Concrete (C1 to C13 up to Plinth)67.88 cu.ft1.92 cum
📊 C. Ground Beam Concrete Quantity (GB1 to GB25)
RCC ground beams as per structural drawing and IS 456
📐 Formula: Ground Beam Quantity = Number × Length × Breadth × Depth
📌 Note: Ground beam dimensions as per drawing. 9"×15" beams have breadth 1.25 ft, depth 1.25 ft. 6"×15" beams have breadth 1.0 ft, depth 1.25 ft.

📊 Ground Beam Concrete Measurement Sheet (GB1 to GB25)

Beam IDNo.Length (ft)Breadth (ft)Depth (ft)Quantity (cu.ft)Quantity (cum)
Ground Beams GB1 to GB25 (9"×15" and 6"×15") - as per structural drawing
GB1 to GB2525As per ground beam schedule drawing197.535.60
Total Ground Beam Concrete Quantity (GB1 to GB25)197.53 cu.ft5.60 cum
📦 D. Total RCC Concrete Quantity (Footing + Column + Ground Beam)
Total RCC Concrete = Footing Concrete (C1-C13) + Column Concrete (Up to Plinth) + Ground Beam Concrete (GB1-GB25)
= 346.26 + 67.88 + 197.53 = 611.67 cu.ft
= 17.32 cum (1 cu.m = 35.315 cu.ft)
S.NoComponentQuantity (cu.ft)Quantity (cum)IS Code Reference
1
注意:
按照完整楼板计算
根据图纸尺寸:23 ft × 36.5 ft
Note: Complete slab calculation - The area includes all spaces between beams. Full plinth area shall be cast.
Isolated Trapezoidal Footing (C1 to C13) 346.26 9.81 IS 456:2000
2 Column up to Plinth (C1 to C13) 67.88 1.92 IS 456:2000
3 Ground Beam (GB1 to GB25) 197.53 5.60 IS 456:2000
GRAND TOTAL RCC Concrete Quantity 611.67 cu.ft 17.32 cum As per IS 1200 (Part 2):1974

📌 Deduction Norms as per IS 1200 (Part 2):1974 Clause 2.1.2:

  • NO DEDUCTION shall be made for volume occupied by reinforcement steel bars (up to 2% of concrete volume).
  • NO DEDUCTION for formwork or small openings up to 0.1 sqm in cross-section.
  • Conclusion: Full measured volume of 611.67 cu.ft (17.32 cum) is billable for RCC concrete work.
💰 RCC Concrete Billing Format & Rate Analysis
As per CPWD DSR 2026 (Indicative Rates for M20 - M25 Grade Concrete)
💡 Note on Rate Analysis: The rate of ₹5,500 per m³ for RCC concrete as per CPWD DSR 2026 already includes contractor profit (15%), water & electricity charges (1%), formwork, mixing, laying, compaction, curing, and all other overheads.

📋 Final RCC Concrete Billing Statement (Footing + Column + Ground Beam)

ParticularsQuantity (m³)Rate (₹)Amount (₹)
RCC Concrete (M20/M25 grade) for Isolated Footing C1-C13 + Column up to Plinth C1-C13 + Ground Beam GB1-GB25 including formwork, mixing, laying, compaction, and curing 17.32 5,500 95,260
Total Basic Cost (Including Contractor Profit & Water Charges) 95,260
Add: GST @ 18% 17,147
GRAND TOTAL (RCC Concrete Only) ₹ 1,12,407
💰 Note: This billing amount is only for RCC concrete work (footings + columns up to plinth + ground beams). Steel reinforcement (rebar) is billed separately as per IS 1786:2008.
❓ Frequently Asked Questions – Footing, Column & Ground Beam Concrete

📌 Common Questions About RCC Concrete Quantity Calculation

1. What is the formula for trapezoidal footing volume?
Total Volume = Bottom Rectangular Volume + Trapezoidal Volume. Trapezoidal Volume = h/3 × (A₁ + A₂ + √(A₁×A₂)).
2. Which IS code governs RCC concrete measurement?
IS 456:2000 for concrete specifications and IS 1200 (Part 2):1974 for measurement.
3. Is there any deduction for reinforcement in concrete billing?
No. As per IS 1200 (Part 2):1974 Clause 2.1.2, no deduction for reinforcement up to 2% volume.
4. How many footings are included in this calculation?
13 isolated trapezoidal footings (C1 to C13) - total 346.26 cu.ft (9.81 cum).
5. What is the volume of columns up to plinth?
Total column concrete up to plinth level is 67.88 cu.ft (1.92 cum) for C1 to C13.
6. How many ground beams are included?
25 ground beams (GB1 to GB25) - total 197.53 cu.ft (5.60 cum).
7. How do I get the Excel BOQ sheet?
Join our WhatsApp channel using the green button on this page, then the Excel download button activates.

📊 RCC Concrete Quantity Summary (As per IS 456:2000)

Isolated Trapezoidal Footing (C1-C13)
346.26 cu.ft
9.81 m³
Column up to Plinth (C1-C13)
67.88 cu.ft
1.92 m³
Ground Beam (GB1-GB25)
197.53 cu.ft
5.60 m³
GRAND TOTAL RCC
611.67 cu.ft
17.32 m³
💰 Estimated Billing Amount (Including GST @ 18%)
₹ 1,12,407
(Rate: ₹5,500/m³ + GST)
Deductions Applied: NIL (As per IS 1200 Part 2 Clause 2.1.2 – No deduction for reinforcement steel bars)
RCC Concrete Quantity Calculation RCC Concrete Quantity Calculation Reviewed by civil engineer on May 18, 2026 Rating: 5