RCC work between plinth level to first slab level

RCC Concrete Quantity | Column, Lintel, Beam & Slab Estimation | IS 456

📜 RCC Concrete Measurement Sheet (IS 456:2000)

IS 456 : 2000 IS 10262 : 2019 IS 4926 : 2003

🏗️ Plinth to First Slab Level

🏗️ RCC Concrete Quantity | Column, Lintel, Beam & Slab Estimation

Project: Concrete from Plinth Level to First Slab Level | As per IS 456:2000 | Rate: ₹7,145.80 per m³

First Slab Drawing
🏗️ First Slab Working Drawing
First Slab Schedule
📋 First Slab Beam Schedule

📐 Column Concrete – Plinth Level to 1st Slab

ColumnNoLength (ft)Breadth (ft)Height (ft)Volume (cu.ft)
C1,C1020.751.251018.75
C2,C4,C5,C7,C8,C960.751.251056.25
C3,C1120.7511015.00
C610.751.25109.375
C1210.751107.50
C1310.751107.50
Total Column Concrete114.375 cu.ft
✅ Column Concrete = 114.375 cu.ft = 3.239 m³

🏗️ Lintel Beam & Chajja Concrete – Ground Floor

ElementNoLength (ft)Breadth (ft)Depth (ft)Volume (cu.ft)
at W3260.750.54.5
LB4 & SB4 (with chajja)220.50.750.7523.0625
chajja for elevation120.53.250.2516.65625
LB1 (at C11 to C12)19.50.750.53.5625
chajja at LB1111.51.250.253.59375
LB2111.250.750.756.328125
LB3110.750.750.5625
LB1 (Front door)111.50.750.54.3125
LB1 (C7 to C10)113.250.750.54.96875
chajja elevation112.251.250.253.828125
LB1 (C3 to C4)151.250.754.6875
LB5 (toilet)23.50.37512.625
LB5 (bedroom)13.750.37511.40625
LB5 (store)13.50.37511.3125
STB1220.751.253.75
STB2180.751.257.5
Total Lintel & Chajja88.86 cu.ft

📌 First Slab Beam Concrete (B1 to B24) - With Dimensions

Slab Beam Details (Length × Breadth × Depth)

BeamLength (ft)Breadth (ft)Depth (ft)Volume (cu.ft)
B1a9.750.751.259.140625
B19.750.751.259.140625
B211.250.751.2510.546875
B370.51.254.375
B411.250.751.2510.546875
B59.50.751.258.90625
B611.250.751.2510.546875
B79.50.751.258.90625
B911.250.751.2510.546875
B109.50.751.258.90625
B1111.250.751.2510.546875
B126.250.7514.6875
B1313.50.751.2512.65625
B1412.50.751.2511.71875
B14a4.250.751.253.984375
B1510.751.250.9375
B166.250.751.255.859375
B1713.250.751.5014.90625
B1812.50.751.5014.0625
B18a4.250.751.253.984375
B197.750.51.254.84375
B206.50.751.256.09375
B213.250.51.252.03125
B225.250.7513.9375
B2313.250.751.514.90625
B247.750.751.257.265625
Total Slab Beams Concrete229.15 cu.ft
✅ Slab Beams Total = 229.15 cu.ft = 6.490 m³

🏢 1st Slab Concrete (S1 to S4)

📋 Slab Concrete Measurement Details

Slab ZoneDimensions (ft x ft)Thickness (ft)Volume (cu.ft)
S13.25 × 9.750.33310.5625
S2 main9.75 × 12.50.37545.703125
S1 at B5-B79.5 × 3.250.33310.29166667
S2 at B139.5 × 10.250.37536.515625
S2 at B129.5 × 6.250.37522.265625
S3 at b187.75 × 3.50.3339.041666667
S3 Sunk slab at B27 × 40.3339.333333333
S3 Sunk slab at B244 × 3.250.3334.333333333
Open passage bath/w.c2.5 × 3.250.3332.708333333
S1 at B203.58 × 6.50.3337.756666667
S411.25 × 13.250.37555.8984375
S1 at B1111.25 × 5.250.33319.6875
Cantilever at C1214 × 1.50.3337
Cantilever extra6 × 1.50.3333
📊 Total Slab Concrete Volume = 665.113 cu.ft | 18.852 m³

📊 Abstract Sheet | Bill of Quantities (BOQ)

RCC Concrete Cost Summary (Plinth to First Slab)

ItemQuantity (cu.ft)Quantity (m³)Rate (₹/m³)Amount (₹)
Column Concrete114.3753.2397,145.8023,140
Lintel Beam & Chajja88.862.5177,145.8017,983
First Slab Beam229.156.4907,145.8046,376
Roof Slab (S1-S4)665.1118.8527,145.80134,686
Total (Excluding GST)1,097.50 cu.ft31.098 m³₹ 2,22,185
Add: GST @ 18%₹ 39,993
Grand Total (Including GST)₹ 2,62,178
💰 Total Concrete = 31.098 m³ × ₹7,145.80 = ₹2,22,185
➕ GST 18% = ₹39,993
Grand Total = ₹2,62,178

🧱 Concrete Material Consumption Calculator (M10 to M25 Grade)

📌 Enter dimensions → shows volume & materials
* M20(8 bags, 0.45 m³ sand, 0.90 m³ agg per m³)

📥 Download Complete RCC Concrete Excel Sheet

Join WhatsApp to unlock download.

📱 Join WhatsApp Channel First →

❓ Frequently Asked Questions (FAQ)

📌 1. How to calculate concrete quantity for columns?
Column concrete = Length × Breadth × Height. For plinth to 1st slab, height is 10 ft.
📐 2. What concrete grade for RCC as per IS 456?
IS 456:2000 recommends M20 (1:1.5:3) for general RCC works.
💰 3. Cement consumption for different grades?
M10:4.5, M15:6.5, M20:8, M25:9.5 bags per m³.
📏 4. Convert cubic feet to cubic meters?
Divide cu.ft by 35.315. Example: 1000 cu.ft = 28.32 m³.
🧱 5. Standard slab thickness?
4 to 5 inches (0.333 ft to 0.417 ft).
📊 6. How to calculate concrete from L×W×H?
Volume (cu.ft) = Length × Width × Height.
🏷️ 7. What is GST rate on concrete?
GST on RMC is 18% as per Indian tax regulations.
🏗️ RCC Concrete Measurement Sheet compliant with IS 456:2000 | Total: 31.098 m³ | Rate: ₹7,145.80/m³ | GST 18%: ₹39,993 | Grand Total: ₹2,62,178